Title: The surprising effectiveness of earliest operation due-date sequencing
Language: English
Authors: Lödding, Hermann 
Piontek, Andreas 
Keywords: equencing, lateness;lateness;schedule compliance;manufacturing control
Issue Date: 21-May-2017
Publisher: Taylor & Francis
Source: Production Planning and Control 5 (28): 459-471 (2017)
Journal: Production planning & control 
Abstract (english): 
In make-to order production, schedule reliability is very important but still not sufficiently accomplished in industrial practice by the vast majority of companies. It has been known for long that processing the orders at a workstation in the order of their operation due-dates can compensate for lateness in the arrival at the workstation within certain boundaries. The paper analyses the effectiveness of earliest operation due date (EODD) sequencing by comparing it to an optimistic theoretical boundary. The surprising result is that EODD can nearly fully exploit the theoretical potential. It should therefore be used in practice whenever schedule reliability is important, with only few exceptions. Its effectiveness though is increasing with the workstation’s WIP level and thus is in conflict with the objective to reduce WIP levels and throughput times. A simple forecasting model allows to assess the extent to which lateness can be compensated by EODD sequencing and which schedule compliance can be achieved.
URI: http://hdl.handle.net/11420/3613
ISSN: 1366-5871
Institute: Produktionsmanagement und -technik M-18 
Document Type: Article
Appears in Collections:Publications without fulltext

Show full item record

Page view(s)

166
Last Week
48
Last month
1
checked on Sep 27, 2021

SCOPUSTM   
Citations

8
Last Week
0
Last month
0
checked on Sep 25, 2021

Google ScholarTM

Check

Add Files to Item

Note about this record

Cite this record

Export

Items in TORE are protected by copyright, with all rights reserved, unless otherwise indicated.